英文: Combining the experience of bored cast-in-situ concrete pile construction for an approach bridge, this paper discusses the construction control measures for bored cast-in-situ concrete pile in deep soft soil.
中文: 摘要结合某引桥钻孔桩施工的经验,探讨深厚软基区的钻孔灌注桩的施工控制措施。
更详细...
英文: The works included 24 bored piles of 2.5 meters in diameter and 55 meters in depth, 500 meters long underground concrete diaphragm wall of 0.8 meters thick and 25 meters deep, 450 pre-cast concrete pile of 0.5 meters in diameter, 12 meters deep soil excav
中文: 其工程内容包括了24支直径2.5米,深达55米直入岩层的钻孔桩,周长500米,深度25米,厚度0.8米的地下连续混凝土墙,450支直径0.5米预制混凝土桩,12米深开挖,多层水平钢支撑系统,混凝土桩承台及地库底板结构。